First Article Inspection for CNC Machined Parts: What to Check Before Approval

Review a CNC first article inspection report before releasing a batch. Check drawing revisions, measured results, finishing requirements and batch inspection.

By MAVORIX INDUSTRIAL
Machined components with square faces, bores and external threads

A machined housing can arrive with a clean finish and the right bore diameter, yet still refuse to bolt onto the assembly. The bore may take the locating pin, but if the mounting holes sit too far to one side, the bolts will not line up. That is the kind of problem you want to find on a sample, not across a full batch.

First article inspection (FAI) checks one or more parts from the intended production process against the current drawing and agreed requirements. If a prototype was made by a different route, treat it as a trial part unless you have agreed otherwise. The first article inspection report should let you see which features were checked, what the supplier found and what still needs a decision.

Make sure the report belongs to the part on your desk

Start with the part number, drawing revision and sample ID. If you asked for three pieces, you should be able to tell which readings belong to each one. A report for Rev A is not enough to approve a Rev B sample, even if the parts look alike. Check that any drawing changes agreed during quotation made it onto the version the shop used.

Then check the condition of the sample. If the order calls for plating, heat treatment or finish grinding, agree which features are checked after those operations and what evidence is needed for checks that must happen earlier. A bore measured before plating may not answer the question your assembly team has about the finished part.

Match the measurements to the drawing

Ask for numbered callouts on the drawing, often called a ballooned drawing. Each number should point to the corresponding row in the report. For a measured dimension, look for the requirement and the actual result, not just a check mark. A gauge check may instead show pass or fail; the report should identify what gauge or method was used where that matters. ZEISS's first article inspection guideline gives an example of how a buyer can ask for numbered features, actual values and supporting evidence.

Example: Three lines from a dimensional inspection report

These are illustrative readings for a hypothetical machined housing, not results from the parts pictured above.

Drawing calloutRequirement and result
01. Bore diameterRequired: 12.000 to 12.018 mm
Measured: 12.011 mm, pass
02. Shoulder depthRequired: 4.95 to 5.05 mm
Measured: 5.02 mm, pass
03. Hole positionRequired: Ø0.10 mm relative to A, B and C
Measured: Ø0.13 mm, out of tolerance

The first two rows pass, but the third is still open. Ask which sample it affects and how the datums were set up for the measurement. If the result is confirmed, decide with your engineering team whether the supplier should correct the part and submit new readings or request a written concession for a defined quantity. Do not treat a working trial assembly as an automatic waiver of the drawing requirement.

Ask for evidence that matches the feature

For a bearing seat on a precision shaft, a diameter reading does not report runout. If the drawing calls for both, the report should show both, with the reference axis or setup clear for the runout check. Likewise, a thread gauge check does not by itself establish usable thread depth. For a blind threaded hole, agree how both will be checked if both are specified.

Material grade, hardness and surface finish should not be inferred from the appearance of a part. If the order calls for a material certificate or heat-treatment record, ask how it ties back to the sample or lot. If a surface roughness value is specified, identify the surface to be measured. A photo is useful for discussing burrs or scratches; it does not replace those records.

Decide what happens after sample approval

Approve the sample and set the batch inspection plan as two separate decisions. The sample report tells you about the pieces it covers. For the production lot, agree which dimensions or features will be checked again, how parts will be selected, and what records will travel with the order. Also agree which changes, such as a new finish supplier or a drawing revision, call for another sample review.

When obtaining a quote, send the current drawing, the sample and batch quantities, and the features you need reported. State whether you want selected critical dimensions or a complete review against the drawing, plus any required report format. Suppliers can quote these as different services; Protolabs' CNC inspection options show why it matters to specify the scope rather than ask for an "inspection report" alone.

If you are sourcing custom CNC machined parts from China, MAVORIX can help clarify the drawing with suppliers, agree the sample checks and collect the inspection records you request. Send your drawing and inspection requirements to discuss the part before ordering.

FAQ

Is a first article inspection report the same as a dimensional inspection report?

Not necessarily. A dimensional inspection report records results for the features in its agreed measurement scope. First article inspection can also cover material, finish and other drawing or purchase-order requirements. Ask for the scope and any required report format in the RFQ.

Do I need a CMM report for every CNC machined part?

No. The right method depends on the feature, tolerance and what the drawing or order requires. A suitable gauge or micrometer may be enough for a straightforward size check. A coordinate measuring machine (CMM) can help with features such as hole position when the measurement uses the specified datums.

Does an approved first article mean the whole batch passes?

No. Approval applies to the reviewed sample and scope. Agree separately which features to check in the production lot, how many pieces to inspect and what to do if a reading is out of tolerance.